• Do MRP Replanning messages apply to WO that were manually created?

    I have a planned WO that was manually created on 6/3 that was manually created stock went below the safety stock limit on 5/15 my MRP replanning messages have a 120 backword and foreward lead time, and under "replan dates" it's set to "Early" …
  • MRP Settings - Load Calculation and Production Lead Time

    MRP Settings have the load calculation at 26 weeks. The production lead time is set to Routing/Product Lead time From what I can see in the load graphs, I only see load for 6 months. and from the MRP results, I can see that the routing is used for…
  • Demand Horizon and MRP

    Does anyone have a better definition of the demand horizon than what has been in the training material ? Also does anyone know what the affects of having the demand horizon set to 0 means for a manufactured good? Thank you!
  • Consequences of MRP Daily bucket set to 0

    Looking through the training material for MRP, most of the suggestions have the daily bucket set to 30. What are the consequences of having it set to 0 ?
  • MRP not suggesting to build to safety stock

    When I look farther out in my projected stock inquiry, the WOS suggestions do not seem to be suggesting to build the stock to safety stock, but just a reflection of the demand. What settings influence this behavior ? How can I ensure my stock level is…
  • Demand Horizon for "Purchased" Products

    In the product-site record there is a demand horizon. From my understanding, anything before that time MRP considers Firm SOs and anything after is Firm SOs and Forecast Demand. For me this makes sense for the products that are manufactured What…