• Setup routing.

    looking for have routings setup per bottle instead of per minute. They want it to look like a WO done for 500 bottles with a routing of $1 each, will add $500 to the WO for labor. Is it possible?
  • Manufacturing: machine set up optimizing

    Hello, everyone! We are facing an issue during the production scheduler implementation. The customer uses products characteristics to optimize the set-up time. Let’s say it is 5 hours long for a complete machine set-up, then to change from a product…