We are new to the PJC module and when we started to setup the jobs, we ASSUMED that we could add the customer numbers later...i ASSUMED wrong. Now, i have these jobs loaded with transactions and was wondering if there is a way of opening up the job so…
I did the following
- At the contract level I set the Overhead type to Percentage of cost on a job
- set the % to 26.74
- entered and posted a cost and eq transaction
** I anticipated seeing my cost + 26.74% in my GL batch. I only see my cost…