• Labor Costs recorded to WIP Asset

    The client would like use the WIP asset accounts to track Revenue and Costs until a project is completed. Can this be done by Job? How is that set up? The system will only allow Payroll Calculations and Position Job A/C to be in the Direct Expense range…
  • Possible to change posted hours?

    How to correctly allocate hours that were coded to the wrong job number? Do I have to wait for next payroll cycle to reverse the entry? It doesn't change pay at all just where the time is coded to.
  • How are you tracking Committed Costs for Labor, Materials, Subcontracts in Sage 100 Contractor?

    Hi, Below are the qualifications and context of the question to follow: If you are not a Construction Company tracking Committed Costs for WIP and Estimated Cost to Complete then the following may not be relevant. If you are a Construction Company who…