• Printing job statements is cutting off paid dates

    Report 3-4-21 (at least in the Canadian edition) is cutting off the dates when you print the payments. This has been happening for a while, but we were hoping it would get fixed in a subsequent release
  • how is the labor burden calculated in the 6-1-2 reports?

    I am having a difficult time trying to figure out how the labor cost is being calculated on the 6-1-2, labor cost reports. they are varying highly for my designer. the same job had one days work at 31.80$ and another days at 75.20$, regular hours, not…