• Job Cost Report - Paid Status

    Hello, What is the best way to produce a report that shows the job costs that have been paid on a job? I would think you could produce a Job Cost Journal (6-1-2) and filter by the job and by status ("paid"), but it does not allow me to choose a status…
  • Can you get budgets from unapproved change orders to show up on reports?

    Can a custom report be created to pull budgets from unapproved(open) changes into a job cost or summary report? We have jobs where some change order work has been performed before it gets approved.
  • Job Cost Reports in Sage 100 Contractor that include computed payroll that is not posted to g/l

    Anyone know of which reports I can use in Project Management (6-1-2) that will include current payroll that has been computed but not posted? Or for that matter payroll record costs that are not final computed? Thank you.