SCHEDULING tables in X3

Hi all,

We have done a customization where an auto WO is created on another site, once created on original site. In a WO Scheduling when we click the ‘Schedule’ button the following data is populated usually:

 

Can you clarify which tables in specific this scheduling data comes from? Since it is a customization involving an auto WO, the SCHEDULING table was updated, the data is visible here. We need to know once we click the Schedule button on the top right corner which scheduling tables in X3 is considered by planner one while planning.

As some of you might be aware if the scheduling data is empty it gives an intialization error on production scheduler. We have updated the SCHEDULING table but might be missing another table or so; as it is giving an initilaization error for the particular WO. 

Is anyone aware which tables are involved with this SCHEDULING

TIA!