Welcome to the Sage Construction and Real Estate products Support Group on Community Hub! Available 24/7, the Forums are a great place to ask and answer product questions, as well as share tips and tricks with Sage peers, partners, and pros.
Firstly,
We have 3 invoices 11113355, 11113356, 11113357.
Invoice 11113357 was created to hold retainage for the previous two invoices after we received payment and realized retainage should have been held but was not originally.
Therefore when…
We wrote a check to our client to return their share of cost savings on the completed project. How do we decrease the income on the job to reflect this? I charged the check to a misc GL account until I could figure how to this this correctly.
The same Misc. Cash Receipt was entered twice, on different dates.
Since it was not payment towards an AR customer account, how do you correct the duplicate entry?