• Changing Job Cost Methodology

    Need to modify the Cost Codes in Sage 100 CRE. We have TOO many cost codes plus when they were originally set up that person used a 5 diget plus 3 decimal XXXXX.XXX cost code. Much too complicated for our field personnel to get it right. I want to change…
  • Sage Contractor 100 Version 19.2 - Do not create archive file until all prior year data is entered

    FormerMember
    FormerMember
    I did not see any other posts about this and I only was able to find this out by calling into the support line (and waiting for 2 hours) so if this helps someone... Note that with the new version 19.2 Sage Contractor 100 you are not supposed to create…