I am looking to Import several lines, with headers, and hoping someone has a template that is easy to follow.  Not too sure what the Ps and Cs are for or what to enter.  If you have an Excel template and/or detailed instructions, please let me know.  Need to get in a HUGE job ASAP and I don't want to have to manually key in 1,000+ lines.  Thanks for your help.

  • 0
    SUGGESTED

    Hello Linda,

    Have you clicked on "Help" in the Job Cost application? Search for "import estimates" and you'll find the required file structure and layout, what you're referring to as a "template." 

    You can also go to the Sage Knowledgebase and search for Solution ID: 24298 "Is there an example/template of Job Cost's Import Estimate?"  There are two attached files for download in that Solution ID.

    Art Minds
    Independent Senior Consultant
    Pasadena CA

  • 0 in reply to Art Minds

    Thanks Art.  I got those but still not understanding.  What are the "P" and "C" for?  Also, what is the "JCE" file?  I cannot open that one.  I need to see the initial setup of the Excel file and what each column is for.  Also, need to see how headers are entered.  I have 19 floors and with each floor, I have 15 cost codes with estimate dollars for all and some also have estimated hours (units).  Any ideas??

  • +1 in reply to Linda R.
    verified answer

    Hi Linda,

    Your questions are answered in the Knowledgebase Article: P = Cost Code (Phase) (if the cost code is not already set up; C = Cost Code estimate amount.  A link to the Sage Knowledgebase is below, in the footer of this web page. The JCE file is the required naming convention for the Job Cost Estimate import file. 

    Art Minds
    Independent Senior Consultant
    Pasadena CA

  • 0 in reply to Art Minds

    Thank you, thank you!!  Taking a look at that now.  I appreciate your help.  Hopefully I will figure this out, if not, I'll be back :-).

  • +1 in reply to Linda R.
    verified answer

    Hi Linda R, if the above suggested answer helped, please do mark it as verified White check mark (by clicking the "more" button) for the benefit of others in this forum :). Thank you!

    If you have a minute, tell us about your great experience on Sage City, take this short 3 question survey

  • 0 in reply to Art Minds

    Hi Art,

    You were very helpful yesterday so thought I'd see if you could help me with, hopefully, my last question on importing my estimates into Sage 300CRE...

    So everything went ok but wondering .. If I have an extra (in my case a Phase), do I need to have a cost code associated with it?  I put in the following:

    P   1st Level   1st Level  (blank)   04272022 (date) and the rest of the columns are blank.

    After setting up to the 18th Level, below is what I got for all these "headers":

    2022-5477-01     P    1st Level  1st Level                           Invalid Cost Code

    Do I need to worry about this or is it okay that the cost code is invalid (it doesn't have a cost code).