• Progress billing

    I am unable to enter the final payment for a project. The issue started when I posted the final payment on the incorrect month a few weeks ago under progress billing. In trying to correct the error, I went under A/R voided the invoice and voided the cash…
  • Retention doesn't include tax in calculation.

    In Progress Billing if a job is taxable Sage calculates taxes correctly but does not include them in the retention calculation. It calculates 10% of the base rate only. For these taxable jobs I have to create an Excel of the pay app to send to the client…
  • Progress Billing retention calculation method

    Right now our system calculates retention only on the pre-tax amount. Is there a way to tell it to calculate retention on the entire invoice amount, including tax?
  • Test Company Progress Billing

    I am working in Sage 100 Contractor - In my test company trying to learn progress billing. I created, saved, submitted and posted an invoice but when I go in to create the next months bill the application number does not advance.
  • Progress Billing-Line Item Description is too short

    I am in menu 3-7, and am unable to see the complete description of the Line item when the continuation sheet is printed. We have a very particular client that needs everything spelled out and nothing abbreviated and therefore need the entire description…
  • cycle date report -progress billing

    Hello, im looking to find or build a report within progress billing to show the billing cycle of the jobs created on a monthly basis let me know if anyone can help [email protected] thanks in advance
  • Progress Billing Retention not showing on Page 1.

    A customer going live using progress billings has just posted their historical billing. When we looked at report #41 using the standard system report.form the retention isn't showing on page 1 where its supposed to be. I've reviewed the release notes…
  • 3-7 Progress Billing

    Is there a report in 3-7 that shows progress bills that were created the month before?
  • Progress Billing Set up

    Hello, I am using Sage 100 Contractor version 194 and have a question with Progress Billing set up. I currently have a schedule of values for main line items (i.e. General Conditions, Site Prep, Masonry, etc...) I would like these main line items to…
  • HELP ME PLEASE!!!!

    Hi everybody, I'm new to SAGE and I already can see I am in for a battle. I am trying to do progress billing for application 2. My problem is that I need to change some of the amounts in previous complete, but the system is telling me that I cannot…