Day-End will update your vendor costs based on the receipt costs from that day.  Does anyone know if or how to stop that from happening?  Currently we run a macro to Export the vendor tables, run day-end, then re import.  Would be nice to simply avoid the need to do this.

Thx

Parents Reply
  • 0 in reply to Django

    because you can place a PO and it be a month (or more out) and then have vendors update costing after PO is placed.  Then when that old PO comes in, it screws all your costing up again.  Or, if you get a one time special price, you don't want it to affect your everyday price.   It's a very common situation that any distributor should be facing.

    Maintaining in vendor contract prices would be a huge drain on time.  