PJC pass though costs based on timecards

Hi,

Hi we are using Basic projects, Time and Materials, with Accrual-Basis as the accounting method.

In PJC, we upload timecards that reference a number of labor costs that should post to individual categories (there is one to one match). Some of these costs are billed based on the billing rate of the category but there are some costs that should be billed at cost (that is, they are passthrough costs).

How can I configure PJC to achieve this?

Thanks

Marios

  • 0

    Hi,

    Adding to my question:

    By setting the project to Cost plus, I can cater for all cost categories that are passthrough, however, some other categories in the project should have their own billing rate (i.e. they are not cost plus). How can this be achieved within the same project?