Browse By Tags

  • Lot Numbers

    I need to come up with a way to consume containers (what our product is packaged in) when a work order is closed. I have thought keeping the current BOMs for the "master BOM" (bulk BOM if you will) for each product and then doing a second BOM that puts…
  • BOM Component Valuation

    I have a production BOM where I have the same component listed three times. 1. amount of "goop" that is needed to fill the containers for the finished good 2. amount of "extra goop" that is needed to prime the tooling 3. the same "extra goop" to…
  • Routes with long operation times set up

    Most of our routes are set up to track minutes, but when i tried to add a non-cost operation to my route where a product will wait for 7 days, the number format gave me an error. I don't want to have to switch the tracking from minutes to hours to have…
  • Work center resources

    If my work center is set up as a machine, is the # of resources the: # of machines or the number of people to run the machine ?
  • Detail Scheduling Products with similar components

    Is there a way to set up my production boms or routes in a way that indicates that a group of them is of a similar product and should be detail scheduled together to reduce set up time ?
  • RCCP in X3

    Does anyone have a blurb or training guide on RCCP and it's relationship to WO scheduling in X3 ?