If my work center is set up as a machine, is the # of resources the:
- # of machines or
- the number of people to run the machine ?
If my work center is set up as a machine, is the # of resources the:
If we have 5 no of machines with the same capacity with same operations, we can say 5 no of resources under the particular work center.
It is the # of machines.