In comparing one job from one month (APRIL) to the other (MAY) this report showed (APR) JTD costs that actually pulled costs from MAY.
I struggled with this for about 4 hours finding the the entries were in fact correct, with the correct accounting date. I checked on the Job Cost Summary, Cost Spread sheet and JC entri
I was behind in getting months closed, so I have the data within a week of each other.
Has anyone else run into this. This report becomes worthless for cost anylsis if it does not pull by the correct date. Only having a year with Sage I am no expert, but maybe someone else has had this problem. I do not know if anyone ever verified that the report works correctly. I have seen variations when running this report and the month is not closed, but it corrects itself once you post you close and post your entries, or estimate inputs.
Any insight is helpful. Thanks.
Ed