Negative Estimate on a Project in PJC

SUGGESTED

We have a customer that receives grants on Projects and they are wanting to record the amount expected as an estimate, however a negative estimate value cannot be added.  Would anyone have an idea how to apply this?

Thanks

Parents Reply
  • 0 in reply to wheumann
    SUGGESTED

    Hey Wendy.  This is related to a detailed investigation you and I did last year into revenue recognition behaviour.  The user has to recognise a manually entered % of estimated costs.  Essentially the outcome was that introducing revenue changes the behaviour of PJC revenue recognition such that it won't work.  The user therefore sets up all jobs as internal (no customer) so revenue isn't invited to the party.